- Preparation of financial, technical and economic analysis by the relevant authority
- Submission of results of research/analysis by the relevant state authority to the Ministry of Finance and the Agency
- Adoption of decision regarding necessity and visibility on implementation of the PPP project by the Ministry of Finance (MoF) within 45 days from submission by the relevant state authority
- Submission of drafted documents/reports/analysis and report of the Ministry of Finance by the relevant state authority to the GoG
- Decision of the GoG on approval, refusal or further amendment to the PPP project